Saudi German Hospital Dammam 84% complete in Q1 2019
03/04/2019
Argaam

Middle East Healthcare Co. (MEAHCO) said the Saudi German Hospital in Dammam was 84 percent complete as on March 31, 2019.
“The project is expected to be completed by June 6, 2019,” MEAHCO said in a bourse statement on Wednesday.
There is no change in the project costs, MEAHCO added.
Actual work on the project began on Dec. 7, 2016.
SGH Dammam is planned as a multispecialty tertiary care hospital with a capacity of 150 beds and 100 outpatient clinics.
In December 2016, MEAHCO awarded a SAR 336.4 million, 30-month contract for the construction of a Saudi German Hospital in Dammam to International Hospital Construction Co.
Related News
| New Saudi German hospital in Dammam to be completed in June |
| Saudi German hospital in Dammam 23% complete |
Market Indices
TASI
10,878.46
13.89
0.13 %
Quotes
SAUDI GERMAN HEALTH
31.04
(0.34)
(1.08%)
Call Request
Comments {{getCommentCount()}}
Be the first to comment
رد{{comment.DisplayName}} على {{getCommenterName(comment.ParentThreadID)}}
{{comment.DisplayName}}
{{comment.ElapsedTime}}