Al Akaria says Al Remal District residential villas 87.4% complete
02/11/2020
Argaam

Saudi Real Estate Co. (Al Akaria) said the residential villas in Al Remal District are 87.44% complete.
The project is expected to be finalized by April 30, 2021, the company said in a bourse statement, noting that there are no variable costs on the delay.
In June 2017, Al Akaria signed a construction contract with its 60%-owned subsidiary, Saudi Real Estate Construction Co., to build 511 residential units at a total cost of SAR 538.28 million in Al-Remal District, according to data compiled by Argaam.
The company previously expected to complete the project by Q4 2019.
Related News
| Al Akaria: Al Remal District residential villas 85.3% complete |
| Al Akaria inks SAR 538 mln contract with subsidiary for Al-Rimal project |
Market Indices
TASI
10,878.46
13.89
0.13 %
Quotes
ALAKARIA
15.60
0.28
1.83%
Call Request
Comments {{getCommentCount()}}
Be the first to comment
رد{{comment.DisplayName}} على {{getCommenterName(comment.ParentThreadID)}}
{{comment.DisplayName}}
{{comment.ElapsedTime}}